DRYCOAL: COMMERCIAL-SCALE TESTING OF A FLUIDIZED-BED DRYING PLANT FOR HIGHLY EFFICIENT LIGNITE-FIRED POWER PLANTS.

Ref.No: 63150800
Start date: 01.10.2004
End date: 31.03.2009
Approval date: 01.06.2005
Department: MECHANICAL ENGINEERING
Sector: THERMAL ENGINEERING
Financier: RESEARCH FUND FOR COAL AND STEEL, E.C.
Budget: 59.236,00 €
Scientific Responsible: Prof. KAKARAS
Email: ekak@central.ntua.gr
Description: THE INTENDED PROJECT COMPRISES THE FOLLOWING MAJOR STEPS: -PLANNING AND DESIGN OF THE COAL PRE-DRYING SYSTEM AND ITS CONNECTION TO AN EXISTING MODERN LIGNITE-FIRED BOILER.-CONSTRUCTION OF THE PRE-DRYING SYSTEM AND CONNECTION TO THE BOILER.........